A bathroom renovation goes in one order: plan and order materials, check for hazardous materials, demolish, rough-in plumbing and electrical, inspect, close the walls, waterproof, tile, paint, then fit fixtures and pass the final inspection. Each stage depends on the one before it, so a step done early or out of turn usually means tearing out finished work. In Ottawa, where many homes predate 1990, the step most people skip is the first one on the site: finding out what is inside the walls before anyone swings a hammer. We run that sequence on bathroom projects across the Ottawa area, with abatement, demolition and renovation under one roof.
TL;DR
- The order is: plan and order materials, hazard check, demolition, plumbing and electrical rough-in, inspection, insulation and wall board, waterproofing, tile, paint, fixtures, final inspection.
- Homes built before 1990 may contain asbestos and homes built before 1991 may contain lead paint, so testing comes before demolition.
- Plumbing and electrical must be inspected before the walls close, and waterproofing must be done before any tile goes up.
- Active construction on a full bathroom typically takes a few weeks, but planning, permits and material lead times add to the total.
- A bathroom renovation with us is priced at $15,000 to $35,000, and hazard work, demolition and rebuild can be handled by one team.
Table of Contents
- The full sequence at a glance
- Stage 1: Plan, budget and order materials
- Stage 2: Check for hazardous materials before anything comes out
- Stage 3: Demolition
- Stage 4 and 5: Rough-in plumbing, then electrical
- Stage 6: Rough inspection
- Stage 7: Insulation and wall board
- Stage 8: Waterproofing
- Stage 9: Tile and grout
- Stage 10: Paint
- Stage 11: Fixtures, vanity and accessories
- Stage 12: Final inspection and punch list
- How long does the sequence take?
- Common mistakes in bathroom renovation order
- Doing the whole sequence with one team
- Our view on sequence
- FAQ
- Sources
The full sequence at a glance
| Stage | What happens | What must be finished first |
|---|---|---|
| 1. Plan and order | Layout, budget, permits, all materials ordered | Nothing |
| 2. Hazard check | Testing for asbestos, lead and mould | Plan and layout |
| 3. Demolition | Strip fixtures, flooring, wall finishes | Clear hazard results |
| 4. Rough-in plumbing | Drains, supply lines, shower valve | Demolition |
| 5. Rough-in electrical | Wiring, fan, lighting, GFCI circuits | Plumbing layout |
| 6. Rough inspection | Inspector reviews open walls | Both rough-ins |
| 7. Insulation and wall board | Walls closed | Passed inspection |
| 8. Waterproofing | Membrane in the shower and wet areas | Wall board |
| 9. Tile | Floor and wall tile, grout | Cured waterproofing |
| 10. Paint | Walls and ceiling | Tile and grout done |
| 11. Fixtures and vanity | Vanity, toilet, faucets, accessories | Cured tile and paint |
| 12. Final inspection | Sign-off and punch list | All of the above |
The logic is simple. Anything hidden behind a surface is built and checked before that surface exists. Anything that can be damaged is installed last.
Stage 1: Plan, budget and order materials
The most common cause of a stalled bathroom job is a missing item, not a missing trade. Tile, vanities, shower glass and specialty fixtures can take weeks to arrive, and a crew that starts demolition before the material is in hand ends up waiting with an open, unusable bathroom.
Do the following before demolition is booked:
- Set the budget. Build in a contingency, because opening walls can reveal rot, old wiring or hazardous materials. Our home renovation budget guide walks through the numbers.
- Draw a complete plan. CAA-Quebec suggests minimum clearances of 30 inches in front of the tub, shower, vanity and toilet, 12 inches on each side of the toilet, and a vanity height of 32 inches. These are worth checking before the plumbing is positioned, because moving a drain later is expensive.
- Choose and order everything. Tile, vanity, toilet, tub or shower base, faucets, fan, lighting and accessories. Confirm dimensions against the plan, since the rough-in depends on the actual fixture.
- Confirm permits. Moving fixtures, adding plumbing, changing wiring or removing walls usually needs permits. The Canadian Home Builders’ Association notes that plumbing, electrical and gas work can legally require licensed contractors depending on the province, and that permits are usually needed. For the Ottawa specifics, see our guide to bathroom permits in Ottawa. We manage permits as part of our renovation work.
If you are still deciding how far to go, from a refresh to a layout change or something bigger, these renovate or rebuild questions help you frame the scope before you plan.
Stage 2: Check for hazardous materials before anything comes out
This is the stage that most generic renovation timelines leave out, and in an older Ottawa house it decides whether your schedule holds.
Health Canada advises caution with asbestos in buildings built before 1990 and with lead-based paint in homes built before 1991. In a bathroom, the usual suspects are:
- Old vinyl or asphalt floor tiles and the adhesive under them
- Plaster and drywall joint compound
- Textured ceilings
- Pipe insulation and vermiculite insulation in nearby attics
- Layers of old paint on trim, doors and walls
Asbestos cannot be identified by looking at it. It takes a sample sent to a lab. Disturbing it by cutting, sanding or breaking it releases fibres, so confirmed asbestos is dealt with under a proper containment plan, not as part of ordinary demolition. Our guide to renovating with asbestos covers the test, contain and clear process in six steps.
We offer testing and lab analysis for $300 to $600. If the lab confirms asbestos, we handle the removal as licensed abatement work. Small Type 1 or 2 jobs, which cover limited, lower-risk work, are priced at $1,500 to $3,500, and larger or Type 3 work is quoted per project. You can see the full range on our abatement services page.
Mould and moisture
Bathrooms are where mould shows up. Look for staining behind the toilet, soft drywall near the tub, and flooring that lifts. The cause has to be found and fixed, otherwise the new bathroom grows the same problem. Surface cleaning does not solve a hidden leak. When growth is more than a small patch, waterproofing alone does not fix it, as we explain in when mould exceeds 1 m².

Our mould remediation is priced at $500 to $1,500 for a small contained area and $2,000 to $6,000 for a single room or bathroom. Flood-related and basement work is quoted per job. Details are on our mould remediation page.
Remediating before demolition, not after, means the rebuild starts on clean framing.
Stage 3: Demolition
With hazards cleared, the bathroom is taken back to the studs and subfloor. Good demolition is more than removal:
- Shut off and cap water supply lines before fixtures come out
- Protect hallways, floors and the path to the door
- Check the subfloor for rot and the joists for damage
- Remove debris daily, not at the end
If you want a non-load-bearing wall opened, the work stays inside the permit rules. CAA-Quebec says a load-bearing wall should only be removed with a qualified specialist, and in Ontario that means involving an engineer before the wall is touched.
A single-room strip-out in our price list runs $1,000 to $4,000, and structural openings run $2,500 to $10,000, depending on the wall. See our demolition page. Debris hauling is part of the work we do, and if you are clearing an old vanity, tub or other bulky items yourself, our junk removal service starts at $75 to $150 for a single item and $150 to $250 for a quarter trailer load.
Stage 4 and 5: Rough-in plumbing, then electrical
Rough-in means the pipes and wires are placed inside open walls and floors, before any finished surface.
Plumbing first. Drains, vents and supply lines have the least flexibility, since drains rely on slope. The shower valve, tub spout location and toilet flange are set to the actual fixtures you ordered. That is why ordering comes first.
Electrical second. Wiring is easier to route around finished pipes. This includes the exhaust fan, lighting, outlets protected by ground-fault circuit interrupters (GFCIs, which cut power quickly if current leaks) and any heated floor.

Both trades should be licensed. Ontario requires electrical work to be inspected by the Electrical Safety Authority, and plumbing is inspected under the municipal permit. The CHBA is clear that gas and electricity work belongs with qualified contractors.
Stage 6: Rough inspection
The inspector looks at the open walls: pipe connections, vent runs, wire routing and any framing changes. This is the last moment anyone can see inside the wall.
Do not close walls until the inspection passes. A failed or skipped inspection after drywall is up means cutting it open again. Skipping it also causes trouble when you sell. Our building code compliance checklist lists what inspectors typically look for.
Permit costs and requirements vary widely between cities. The CFIB’s January 2024 report compared permitting for a powder-room-to-full-bathroom conversion in 12 Canadian municipalities, which shows why it pays to confirm local rules early.
Stage 7: Insulation and wall board
Once the inspection passes, exterior walls are insulated and the walls are closed with moisture-resistant board suitable for wet areas. Seams are taped and finished. Joint compound has to dry before it is primed, and this is where bathrooms pick up a few quiet days in the schedule.
Stage 8: Waterproofing
Waterproofing goes on before tile, never after. Water does not stop at tile and grout. Grout is porous and tile joints are not a seal, so the membrane behind the tile does the real work. CAA-Quebec recommends a waterproofing membrane behind shower tiles and an uncoupling membrane under floor tiles.
The membrane must be fully cured, according to the manufacturer’s instructions, before tile goes on. Rushing this is the most expensive shortcut in the whole sequence, because a leak shows up months later behind a finished wall.
A flood test on the shower base before tiling is a worthwhile habit. It takes a day and tells you whether the base holds water.
Stage 9: Tile and grout
Floors are typically tiled first, then walls, or walls first in a shower, depending on the layout. Plan the layout from the centre of the room so the cuts at the edges look balanced.
Then comes grout, and then the cure. Grout and thinset need time before they bear load. Nothing heavy is bolted to the tile until it has cured, and the manufacturer’s data sheet gives the minimum. Sealing, if the tile or grout needs it, happens at the end of this stage.
Stage 10: Paint
Paint goes on before fixtures so you are not cutting around a new vanity or toilet. Use a moisture-rated paint with a mildew-resistant finish. Let it dry before installing anything that could scuff it.
Stage 11: Fixtures, vanity and accessories
The finishing sequence is usually:
- Vanity and countertop
- Toilet
- Faucets, shower trim and drain hardware
- Mirror, lighting trim, towel bars and accessories
- Glass shower doors, which are often last because they are measured after tile is complete
This is the stage that looks fast and feels like progress, and it is, but only because the earlier stages were done in order.
Stage 12: Final inspection and punch list
The final inspection closes the permit. Before then, run every tap, flush the toilet repeatedly, run the fan, trip the GFCI, and check for drips under the vanity. Make a punch list of small items. Keep the paperwork: permits, inspection sign-offs and any abatement documentation. We provide post-job documentation, which matters when you sell an older home and a buyer asks what was found and what was removed.
How long does the sequence take?
Timelines depend on scope, trade availability and how many stages overlap. As a rough guide, here is where time goes:
| Phase | Typical duration |
|---|---|
| Planning, design and ordering | Often a few weeks, longer for special-order items |
| Permits | Varies by city and scope |
| Hazard testing and any abatement | Days for testing, longer if removal is needed |
| Demolition | A few days |
| Rough-in and inspection | About a week, depending on inspector availability |
| Wall board, waterproofing and tile | The longest block, because each layer has to dry or cure |
| Fixtures and final inspection | A few days |
A standard bathroom is often a matter of weeks on site, with the total from decision to completion running longer once design, permits and deliveries are counted. The biggest delays tend to be late materials, a failed or late inspection, and surprises behind the walls. Every one of those is reduced by doing the hazard check and ordering first.
For budget planning, our bathroom renovation range is $15,000 to $35,000, and we give an itemized quote so you can see where each dollar goes. Estimates come within 24 hours.
Common mistakes in bathroom renovation order
- Ordering after demolition starts. You wait with no bathroom.
- Demolishing before testing in an older home. One broken tile can turn a routine job into an abatement project, with the cost and delay that follow.
- Closing walls before inspection. It means cutting out finished drywall.
- Tiling over uncured waterproofing. Leaks that appear after everything is finished.
- Installing the vanity before paint or tile. Damaged finishes and awkward cuts.
- Changing the layout mid-project. A moved drain affects every stage after it.
Doing the whole sequence with one team
The sequence has a lot of handoffs: testing, abatement, demolition, trades, inspections, finishing. Every handoff is a place where schedules slip. We handle abatement, demolition and renovation under one roof, and we manage permits, air quality testing, debris hauling and post-job documentation. With 25+ years of local experience and a 5.0-star Google rating, we aim to keep a bathroom job moving in the right order.
If you own an older Ottawa home, the best first step is a free estimate. Tell us what you want to change, and we will start with what is behind your walls. You can see the work on our renovations page or start at hmjcontracting.com.

Our view on sequence
Most bathroom problems we are called to fix did not come from bad tile or a bad faucet. They came from an order-of-work mistake: a wall closed before it was inspected, a membrane that was rushed, or demolition that began before anyone knew what was in the plaster.
In Ottawa, many houses were built when asbestos and lead paint were common. We think the hazard check belongs at the very start of a bathroom project, not as a surprise halfway through. When the same company that tests can also remove, demolish and rebuild, the schedule has fewer gaps and the paperwork is in one place.
We also believe in itemized, line-by-line quotes. When you can see each stage priced, you can follow the sequence on paper before it happens on site.
Jason
FAQ
In what order do you redo a bathroom?
Start by planning and ordering materials, then check for hazardous materials and demolish. Rough in plumbing and electrical, pass the inspection, close the walls, waterproof, tile, paint, and finish with fixtures and the final inspection.
Do I need a permit to renovate my bathroom in Ottawa?
If the work changes plumbing, electrical or structure, you will usually need permits. A simple cosmetic update generally does not. Check the rules with the City of Ottawa before you start, or read our renovation permit application guide. We manage permits on our renovation projects.
Should asbestos testing happen before demolition?
Yes, in any home built before 1990. Asbestos cannot be confirmed by sight, so a sample goes to a lab before work begins. Testing and lab analysis with us is $300 to $600.
Can I renovate a bathroom in a different order to save time?
Some tasks overlap, such as ordering while testing is under way, but the dependencies are fixed. Inspections come before closed walls, waterproofing before tile, and fixtures after cure and paint.
Sources