Change Orders Explained for Ottawa Renovation and Abatement

By HMJ Contracting · Ottawa, ON

Homeowner and contractor review bathroom change

A change order is a written amendment to your construction contract. It records a change to the work, what that change costs or saves, and how it moves the schedule, and it is signed before the changed work starts. On a renovation or abatement project in an older Ottawa home, change orders are the normal way to deal with what nobody could see on quote day: asbestos under old flooring, mould behind a tub surround, or a wall that turns out to carry load. We explain how they work, what a good one contains and how to keep the final bill predictable.

Hmjcontracting
Keep Renovation Changes Clear
HMJ Contracting provides abatement and renovation services for Ottawa homes, with detailed, itemized quotes to help clarify project costs.
Visit

TL;DR

  • A change order is a signed, written amendment to the contract that states the change in the work, the price adjustment (or how it will be calculated) and the effect on the schedule.
  • Changes come from two places: something you decide to add or remove, or a condition nobody knew about until work opened up the house.
  • Nothing changed should be built until the order is agreed in writing. A verbal “go ahead” is where most disputes start.
  • Industry guidance recommends a quick turnaround: a priced quotation within 7 days and a decision within 14.
  • A detailed, line-by-line original quote is the baseline every change order is measured against, so it is worth getting right first.

Table of Contents

What a change order is

Your contract describes a scope of work (what will be built or removed), a price and a time frame. A change order amends one or more of those. The Manitoba Construction Association’s protocol, for example, defines it as a written contract amendment that states the parties’ agreement on a change in the work and any adjustment to price or time. The Construction Association of Nova Scotia’s guideline describes changes in the same way, as additions, substitutions or omissions from the original scope.

Two points follow from that definition.

First, a change order can reduce the price as well as raise it. If you drop the tile backsplash or switch to a simpler vanity, the credit goes into the same document.

Second, a change order is an agreement, not a request. The contractor may tell you a change is needed, and you may ask for one, but it only becomes a change order once both sides have agreed on the work, the money and the time. The Nova Scotia guideline puts it that way: an order is issued when the parties agree on scope and schedule and on a price or a method for determining it.

You may also see the terms “variation” or “contract amendment”. In residential work they all point to the same thing: a written record of what changed.

Why changes happen on a renovation

The Ontario Construction Association’s contractor guide says a change arises either because the owner wants to introduce one or because an unknown or unanticipated condition occurs. The Nova Scotia guideline lists the usual areas: design, quantities, quality, working conditions and the sequence of work. It also names an inadequate description of the required work in the contract as a source of changes. That last point matters to homeowners, because a vague quote produces more change orders than a detailed one.

Common causes of renovation change orders

Changes you choose

These are the easiest to manage because you control the timing. Typical examples in a home:

  • Upgrading cabinets, countertops or flooring after the contract is signed.
  • Adding pot lights, a second sink or a heated floor.
  • Moving a wall or adding an opening, which can also involve structural demolition and a permit.
  • Removing something from the scope to save money.

The cost of a late decision is mostly timing. A tile change requested after the order has been placed is a different conversation from the same change requested before it.

Conditions nobody could see

In Ottawa, much of the housing stock is old enough to contain materials that are hazardous when disturbed. Opening a wall or lifting a floor can reveal:

  • Vermiculite insulation in an attic, which can be a sign of asbestos.
  • Asbestos-containing materials such as old flooring, textured ceilings or pipe wrap.
  • Mould behind a tub, under a window or in a basement after water damage.
  • Lead paint on trim and walls.
  • Rotted framing, outdated wiring or plumbing that does not meet current requirements.

When one of these turns up, the work has to stop or change, and a change order records what happens next. Our guide to examples of unexpected renovation discoveries walks through the most common ones.

Change request, change directive and change order

These three terms get mixed up, and the difference decides when work can start.

Term What it is Is the price agreed?
Change request One side proposes a change and asks for a price and time impact No
Change directive Written authorization to proceed with the work before the price and time are settled No, still being negotiated
Change order The signed amendment that records the agreed work, price and time Yes

The Manitoba protocol describes a directive as written owner authorization to go ahead before price and time adjustments are agreed, with the parties continuing to negotiate and recording the outcome in a later change order. The same protocol notes that a directive covers work within the general scope of the contract, while a change order can cover a change outside it, and that the contract’s own terms govern.

For a homeowner the practical lesson is that a directive leaves the price open. The protocol’s guidance is to prefer change orders to directives and to pursue final pricing promptly. In a home project that means: agree the number first whenever the schedule allows, and use a directive only when delaying would cause damage or leave the house unsafe.

What a written change order should contain

A good change order is short, but it is specific. Based on the Manitoba protocol, which says to record the agreed change in the work, the method or amount of any price adjustment and the extent of any time adjustment, a homeowner can check for these items:

  1. A description of the change. What is being added, removed or substituted, and where in the house. “Extra work in bathroom” is not enough. “Replace 2.4 m of water-damaged subfloor and joists under the tub” is.
  2. The price effect. A fixed amount, or a stated method such as a unit price. Every cost should be a line you can read, not a lump sum.
  3. The schedule effect. The number of days added or removed, or a statement that the date does not change.
  4. What it replaces. Which line of the original quote it adjusts, so credits for removed work are visible.
  5. The revised contract total. Original price, this change, and the new total.
  6. Signatures and date. Both parties, before the work begins.

The protocol also says the information needed to assess the price and time effects should be provided, and that any assumptions about the date of authorization should be stated. In plain terms: if the crew is waiting for your signature, the order should say how long a delay in signing pushes the schedule.

How the price can be set

Municipal contract conditions show the common pricing methods. Halifax’s January 2025 conditions, written for civil works but a useful illustration of the options, allow changes to be valued by an accepted lump sum, agreed unit prices, cost plus a fixed or percentage fee, or variation of contract unit prices. The same conditions say changed work that matches scheduled quantities and unit prices is paid on the same basis as the original work.

On a home project, the equivalent options are:

  • Fixed price for a clearly defined change, such as adding a pot light circuit.
  • Unit price when the quantity is uncertain, such as per square foot of rotted subfloor or per linear foot of framing.
  • Cost plus a stated fee when the extent cannot be known until the area is opened. Ask for the fee percentage in writing and for receipts.

Unit prices are the easiest to compare, which is why it helps when the original quote already contains them. We publish ranges for many of our services so you can see what is typical before a quote arrives: for example, mould remediation for a single room or bathroom is listed at $2,000 to $6,000, and testing and lab analysis at $300 to $600.

A worked example: a bathroom that was not what it seemed

Say you sign a bathroom renovation. Our published range for a bathroom renovation is $15,000 to $35,000, and in this example your contract is for $24,000. The itemized quote covers demolition, plumbing, waterproofing, tile, fixtures and finishing.

On demolition day the crew removes the tub surround and finds mould on the back of the wall and damp framing. Here is how a clean change process goes, using an illustrative figure and not a quote:

  1. Work stops in the affected area. The crew documents the condition with photos and tells you the same day.
  2. The cause is identified. Testing may be needed to confirm what the material is. Lab analysis is listed from $300 to $600 for abatement-related testing.
  3. A priced proposal arrives. It separates the remediation of the contained area from the repair of any damaged framing, so you see two lines, not one.
  4. You approve or adjust. You sign the change order, which states the added cost, any added days and the new contract total.
  5. Work resumes. The original lines for demolition and rebuild stay as they were, apart from anything the change replaced.

If the remediation were a small contained area, our published range is $500 to $1,500. A single room or bathroom is $2,000 to $6,000. A basement or flood-related job has no published price because the extent varies too much to list. Whatever the scale, the principle is the same: a defined area, a defined price, a signature, then work.

If the discovery is asbestos, the stakes are higher. Materials containing asbestos should be handled by licensed, insured abatement crews, and the contractor needs to stop the affected work until it is dealt with. Hazardous-material findings are a legitimate reason for a change order, and also a reason not to disturb the area while you wait for it.

A worked example: a bathroom that was not what it seemed

The step-by-step process

The research on change orders agrees on the main sequence. Here it is in the order it should happen on your project.

1. Flag the change early

The first step is to identify and track a potential change as soon as it arises, whoever raises it. The Manitoba protocol also notes that the contract’s own terms take precedence over its guidance, so read the change clause in your contract before anything else.

2. Ask for a written price and time impact

Industry guidance suggests a 21-day cycle: the contractor submits a prepared quotation within 7 calendar days, and the owner approves or rejects within 14 calendar days, according to the Manitoba protocol. That is a recommendation for the industry, and a small home job often moves faster, but it gives you a reasonable expectation: you should not wait weeks for a number, and you should not be pressed to decide the same afternoon unless there is a safety reason.

3. Compare it with the original quote

Open the original itemized quote beside the change proposal. Check that nothing is charged twice, that removed work is credited, and that the unit prices match where the same work appears in both. This is where a line-by-line quote pays off. Our guide on what a renovation quote breakdown includes shows what to look for.

4. Check permits and approvals

Some changes need a building permit or an amended one: moving a wall, adding an opening, changing plumbing or electrical. Changing the scope without checking can delay inspection. Our renovation permit application guide covers how this works for Ottawa projects.

5. Sign before work starts

Both parties sign and date the order. Halifax’s conditions show how firm this principle can be in formal contracts: changes require written orders, and price or time claims are invalid unless the change was ordered and valued, or agreed to be valued, under the contract. That is a municipal contract, not a rule for your home, but the logic carries over: a change nobody put in writing is hard to price afterwards.

6. Update the schedule and budget

A change order that adds days affects everything behind it: trades, deliveries, and how long you live without a kitchen. See our home renovation timeline guide for how changes ripple through a schedule, and keep a contingency in your renovation budget so a justified change does not become a financing problem.

How to avoid disputes

Most disagreements about change orders are about paperwork, not about the work. The same protocol’s prevention advice reduces to a short list:

  • Track changes from the moment they appear, not at the end of the job.
  • Follow the contract’s change procedure exactly.
  • Choose change orders over directives wherever you can.
  • Settle the final price promptly.
  • Keep records: photos, dated messages and the schedule, because time-related costs depend on them.

For homeowners, add two habits. Keep every signed order with the contract so you always know the current total. And define scope tightly at the start. A precise scope of work leaves fewer gaps for changes to fill, which is the point of our guide on how renovation scope of work is defined.

Perspective

Most homeowners we meet are not worried about a change order itself. They are worried about being surprised. That is why we build the process around a detailed, line-by-line quote and clear communication from the first estimate.

An itemized quote does real work later. When an old house reveals something unexpected, you and we can both point to the line that was in the contract and the line that is new. There is no argument about what was included, because it was written down.

Older Ottawa homes are where this matters most. Because we handle abatement, demolition and renovation under one roof, a discovery of asbestos, lead or mould does not mean you start looking for a second company mid-project. The testing, the containment and the rebuild are planned together, and the documentation after the job is part of the work.

Our advice: ask for the price in writing, ask what it replaces, and sign before work begins. A good contractor will want that as much as you do.

Jason

Getting a renovation or abatement quote that holds up

We are an Ottawa-area contractor handling licensed and insured abatement, renovations, demolition, junk removal, and deck and fence installation. Our estimates are free, and we aim to provide them within 24 hours. Quotes are itemized line by line, so every change order has a clear baseline to start from. If your house is older and you plan to open walls, start with the abatement services page or the renovations page to see typical price ranges, then request an estimate.

Hmjcontracting

We also haul away debris and unwanted materials, with single-item pickups listed from $75 to $150 and a full trailer load at $450 to $700, so a change that creates extra waste does not leave you with a pile in the driveway. Our junk removal page has the details. Whether you are a homeowner, property manager or commercial owner, the starting point is the same: the full scope in writing, then any change in writing too.

FAQ

What is a change order in simple terms?

It is a signed document that changes your original construction contract. It states what work is being added, removed or substituted, what that does to the price and what it does to the schedule. Both you and the contractor agree to it before the changed work starts.

Do contractors overcharge for change orders?

A change order is only as fair as the quote behind it. When the original quote is itemized and the change proposal uses the same unit prices and shows credits for removed work, you can see exactly what you are paying for. Ask for the price method in writing, whether fixed, unit-based or cost plus a stated fee.

Can a change order lower the price?

Yes. The Nova Scotia guideline describes changes as additions, substitutions or omissions, so removing work from the scope is a change like any other. A credit for omitted work belongs in the same written document as any increase.

What is the difference between a change directive and a change order?

A directive is written authorization to start the work before the price and schedule effects are agreed. A change order records the agreement once the price and schedule are settled. The Manitoba protocol recommends choosing change orders over directives where possible, because a directive leaves the final price open.

How long should it take to get a change order approved?

The Manitoba protocol recommends a 21-day cycle: a priced quotation from the contractor within 7 days and a decision from the owner within 14. On a residential job the timing is usually shorter, and your contract’s own change clause sets the rule that applies to you.