Deck Footing Depth: How Deep to Dig in Ottawa and Across Canada

By HMJ Contracting · Ottawa, ON

Deep deck footing hole beside a house

For a deck that is attached to your house, or that sits more than 600 mm (about 2 ft) off the ground, footings must go at least 1.2 m (about 4 ft) below grade. They must also go below the local frost depth if that is deeper. Municipal guides in Ontario state that figure as 48 in (1.2 m) under Ontario Building Code 9.12.2.2. Clay soil does not change the minimum, but it is a reason to follow the local figure strictly. The rest of this guide explains the exceptions, what the inspector checks and how to plan the work. We build decks across Ottawa and Renfrew County, so the examples lean local.

Hmjcontracting
Plan Your Ottawa Deck Project
HMJ Contracting offers full-service renovation work for Ottawa homeowners planning deck projects and other property improvements.

TL;DR

  • Attached decks, and any deck more than 600 mm above ground, need footings at least 1.2 m (4 ft) deep and below frost penetration.
  • Small, low, freestanding decks with no roof can be exempt from the minimum depth, but only if all the conditions are met.
  • Frost depth is set locally, so the number that counts is the one your municipality’s building department accepts.
  • Clay holds water and heaves in frost, so depth, footing size and an inspection before the concrete is poured all matter.
  • Footings are inspected before concrete goes in. Schedule that inspection before you dig.

Table of Contents

Why footing depth matters at all

Water in the soil freezes in winter and expands. A footing that sits inside the frozen layer gets pushed up, and when the ground thaws it does not settle back evenly. One post rises, another stays put, and the deck goes out of level. If the deck is attached to the house, the ledger board (the beam bolted to the house wall) is dragged with it. That can damage the wall, the door threshold and the guards.

The frost depth is the deepest point at which ground typically freezes. Footings go below that point so that they stay in ground that does not move. That is the whole logic behind the 1.2 m number and the reason it is a floor, not a target.

The code rule: 1.2 m or below frost, whichever is deeper

The National Building Code of Canada, and the provincial codes built on it, set the rule in Part 9, Table 9.12.2.2. For foundations with no heated space on clay or undefined soil, the table calls for at least 1.2 m depth and not less than frost penetration. The Vancouver by-law reproduces that table. Foundations on silt or poorly drained coarse-grained soil must extend below frost penetration. Rock and well-drained coarse-grained soil (clean gravel, for example) have no minimum depth.

The Ontario version is repeated in many town deck guides. Port Hope’s Deck Design Guide says a deck attached to a dwelling, or one that needs a guard, has a minimum footing depth of 48 in (1.2 m). Outside Ontario the figure is the same. Yarmouth, Nova Scotia requires a foundation below frost level with a 1.2 m (4 ft) minimum depth for a deck attached to a dwelling.

An inch or two of rounding between 47 in and 48 in is not what you should worry about. The point is that 1.2 m is the starting number everywhere, and your local frost depth can only raise it.

The code rule: 1.2 m or below frost, whichever is deeper

When a deck is exempt from the minimum depth

The code lets some small decks skip the frost-depth rule. Rosetown’s deck foundation document lists the conditions. The deck must be:

  • no more than one storey,
  • no more than 55 m² (592 ft²) in area,
  • no more than 600 mm from finished ground to the underside of the joists, and
  • not supporting a roof.

The code also says the deck must not be attached to another structure, unless it can be shown that movement of the deck will not harm that structure. The BC Building Code’s Section 9.12 states this. Port Hope adds that a pergola or trellis counts as a roof. Its guide also says frost protection is not required only if the deck is under 24 in (600 mm) high, not attached to any structure, not supporting a roof and no larger than 55 m².

Miss any one condition and the exemption is gone. Most backyard decks in Ottawa fail at least one of them. They are attached to the house, or they are higher than 600 mm, or they are meant to take a pergola later. If you might add a roof, size the footings for it now.

Also remember that a deck being exempt from frost depth is not the same as being exempt from a permit. Our guides on whether you need a deck permit in Ottawa and on Ottawa deck building permit requirements cover that separately.

Frost depth is local, so ask the local inspector

The code gives the 1.2 m minimum but does not hand you a frost depth for your street. That depth is set locally, and municipalities publish their own figures. They differ:

Municipality or authority Published footing depth Source
Laurentian Valley, Ontario (Renfrew County) 48 in (about 1.2 m) below grade Township deck guide
Kingston, Ontario 1.2 m below ground City deck permits page
Grimsby, Ontario At least 1.2 m below finished grade Footing inspection checklist
Cariboo Regional District, BC 1.07 m (3 ft 6 in) CRD building permits guide

The Cariboo figure shows that the national 1.2 m is not a universal constant. Colder regions go deeper and some milder ones publish less. For Ottawa, confirm the depth with the City of Ottawa’s building code services before you dig, because that is the figure your inspector will hold you to. The Cariboo guide itself points homeowners to Environment Canada’s climate data for frost information.

In practice, always plan for at least 1.2 m. If the City or your inspector says deeper, that is the number.

Clay soil and drainage

Much of the Ottawa area sits on clay, which is the soil type that the code ties to the 1.2 m minimum. Clay holds water, and wet soil is exactly what heaves when it freezes. Three practical points follow.

Go to undisturbed ground. A footing should sit on solid, clean, unfrozen ground. Grimsby’s inspection checklist lists that along with the 1.2 m depth. If the bottom of the hole is soft, wet or loose fill, dig deeper or ask the inspector what is acceptable. Laurentian Valley’s guide says footings must bear on solid ground at a minimum of 48 in below grade, deeper if solid ground is not found, and that the Building Inspector verifies bearing conditions before concrete is placed.

Size the footing for the soil. Municipal guides work from a soil bearing capacity of 75 kPa, which is a standard conservative assumption for ordinary soil. Port Hope’s guide says the minimum bearing area must be doubled where a high water table affects soil bearing capacity. Ramara’s guide says the same. It also says that in hard clay or on bedrock a pier may bear directly on the solid base, while piers in sandy or loose soils need a footing. A footing here is the wider concrete pad under the pier that spreads the load.

Manage the water. Drainage next to a footing affects how the soil behaves. For a plain-language explanation of how soil type and drainage change what a foundation needs, see this piece on soil type and drainage effects on foundations. Keep roof runoff, downspouts and grading from sending water to the deck footings.

Other things that change the footing, not just its depth

Depth is one number. Footings also need the right size, spacing and concrete.

  • Pier diameter. Ramara requires piers at least 9 in in diameter, and Port Hope requires at least 10 in. Kingston’s guide specifies 230 mm sono-tubes, the cardboard forms that shape poured piers.
  • Height above grade. Piers should not extend more than three times their width or diameter above grade, according to Port Hope and Ramara. Kingston leaves tubes 150 mm above ground, and Laurentian Valley specifies 6 in.
  • Spacing. Laurentian Valley allows a maximum pier spacing of 10 ft (3 m), and calls for a minimum 28 in by 28 in footing where spacing exceeds 10 ft.
  • Concrete strength. Port Hope specifies poured concrete with a minimum compressive strength of 5 MPa (2200 psi) at 28 days.
  • Loads. Port Hope’s guide calls for special consideration where a deck carries a hot tub or similar structure, because of the extra weight. Covered decks need a footing under the pier too. Kingston requires one at the pier base if a roof is added or soil bearing capacity is exceeded.
  • Screw piles. Some jurisdictions accept auger-installed steel piles. Brandon’s December 2025 bulletin says sealed plans may not be required for CCMC-evaluated piles supporting up to 5,000 lbs each, and loads above that need sealed plans and an engineer’s certification letter. Rules for these systems vary by municipality, so check yours.

Wood posts have their own requirements. They must be kept off direct contact with the ground and the concrete, unless treated with a preservative. Edmonton’s design guide says exterior wood stairs must be isolated from direct ground contact unless treated.

Do deck stairs need footings?

Yes, the bottom of the stairs needs solid support. Edmonton’s guide says stair stringers must be well supported at the top and bottom, with proper connectors, and that stairs be isolated from ground contact unless treated. In practice that means a concrete pad or pier under the stringers, not untreated wood sitting in soil. Because stairs are attached to the deck, ask your inspector whether the stair support must also go below frost. A stair pad that sits on the surface can move seasonally while the deck stays put, and that opens a gap at the bottom step.

What the inspector checks, and when

Footing inspections happen before the concrete is poured, and that timing catches people out.

  1. Permit application. Plans should show footing size, spacing and depth below grade, post sizes and spacing, beam and joist details, deck height above grade and stair details. Kingston’s checklist lists these items.
  2. Footing inspection. Kingston requires the footing inspection to be booked before holes are filled with concrete, at least 24 hours ahead. Laurentian Valley inspects footings before concrete is placed too, then the framing, then a final inspection before use.
  3. Framing and final inspections. These come after the structure is built, before top boards and guards are completed in Kingston’s process.

If you pour first and call afterwards, you may be asked to open the footings up. Laurentian Valley also notes that any deviation from its typical details requires plans sealed by a Professional Engineer or a designer sheet signed for the Building Structural category.

A simple sequence for planning your footings

  1. Decide the deck type. Attached, freestanding, height above ground, any future roof or pergola, any hot tub. This tells you whether the exemption can apply at all, and for most decks it will not.
  2. Get the local depth in writing. Ask the building department what frost depth and minimum footing depth apply on your lot, and whether a permit is needed.
  3. Locate the posts. Lay out pier locations at or under the maximum spacing allowed. Keep utility locates in mind before you dig.
  4. Dig to solid, unfrozen ground at or below the required depth. If you hit soft clay or fill, keep going or ask the inspector.
  5. Book the inspection. Do it before any concrete is poured, with the notice the municipality requires.
  6. Pour, set and protect. Use the specified concrete strength, keep wood posts separated from wet concrete and do not backfill carelessly against fresh piers.

The same logic applies to fences. Posts also heave if they are shallow, which is why a post-thaw check in spring is worth doing every year.

What this costs

Footing work is part of the deck price and not billed as a separate line on most jobs. Our published range for a pressure-treated deck is $45 to $75 per sq ft, and it covers the work above the ground too. Wood choice changes the total, and we compare materials in our guide to cedar versus pressure-treated lumber. For a wider view of long-term cost, see composite versus wood decking.

Our view on footings

Footings are the part of a deck nobody sees once the boards go down, and they decide whether the deck is level in ten years. We would rather talk about them first than last.

On older Ottawa properties, we often find that a deck was built before the current rules, or that the house wall behind it has other issues. Hazardous materials like asbestos and lead turn up in older homes, and demolition and renovation work belongs under one roof with certified abatement, so the order of work is planned properly. A deck that attaches to an older house deserves that planning.

Our crews handle permit management and give itemized, line-by-line quotes, so you can see the footing work as its own line. We offer free estimates, with a response within 24 hours. Whatever the deck, our advice is the same: get the depth confirmed with the City, book the footing inspection before pouring, and do not shortcut it.

Jason

Have your deck built with the footings done right

We design and build custom decks and fences for Ottawa-area properties, with permit management and post-job documentation included in our services. Our pressure-treated decks are priced from $45 to $75 per sq ft, and cedar and pressure-treated fences are quoted per linear foot. See the details on our decking and fencing page.

Hmjcontracting

If the deck sits against an older house, we can also handle demolition of the old structure and any abatement work first. Request a free estimate through hmjcontracting.com.

FAQ

How deep should deck footings be in Ottawa?

At minimum 1.2 m (about 4 ft) below grade, and below the local frost depth if that is deeper. Confirm the exact figure with the City of Ottawa’s building department, since the frost depth is set locally. Your inspector will hold you to that number.

Do I need to go below the frost line for a low deck?

Only if it does not meet the exemption. A deck that is freestanding, no more than 600 mm above ground to the underside of the joists, no larger than 55 m² and without a roof can be exempt. An attached deck is generally not exempt, because movement could damage the house.

Does clay soil mean deeper footings?

The code’s 1.2 m minimum already applies to clay or undefined soil. What clay changes is how carefully you build: bear on solid, undisturbed ground, keep water away, and double the footing’s bearing area where a high water table is present. Your inspector can ask for more depth on a given lot.

When is the footing inspection done?

Before the concrete is poured. Municipalities like Kingston ask for at least 24 hours’ notice, and Laurentian Valley inspects footings before concrete as well, then framing and a final inspection. Book it before you dig, not after you pour.

Do deck stairs need footings?

Yes, the bottom of the stringers needs solid support, such as a concrete pad or pier. Wood must not sit untreated in direct ground contact. Ask your inspector whether the stair support must go to frost depth too.